Skip to Project List

MobilityWorks 2.0

Overview

Total Estimated Revenues

$488,675,000

Total Projects

17

Revenues Received

$6,010,087.39

Expenditures to Date

$1,266,091.82

Active Projects

7

Jobs Created by Program

Actual Goal
2000
1500
1000
500
0
Transit
Roadway

Transit

Actual 0
Goal 1751

Roadway

Actual 0
Goal 153

Screen Shot 2022 11 01 At 2 20 33 Pm
A combination of jobs created by JTA, Jacobs and sub-consultants: Actual jobs created in Transit, 3. Actual jobs created Roadway, 6. ***This comprehensive program developed by the U.S. Department of Transportation (DOT), which establishes guidelines for the participation of firms owned and operated by socially and economically disadvantaged persons in DOT-assisted contracting. Disadvantaged Business Enterprise (DBE) Program

LOGT Project Status

Status Projects
Pending
10
Planning
7
Design
0
Construction
0
Complete
0

Status

Projects

*The expenditures to date have been set aside but not yet paid to the vendor.